When a generator is tagged out, what is a recommended step?

Prepare for the WMSL In-Port Engineer Officer of the Watch Test. Use flashcards and multiple choice questions with hints and explanations. Start your journey today!

When a generator is tagged out, the recommended step is to notify the engineering officer. Proper tagging out procedures are critical to ensure safety and operational integrity. Notifying the engineering officer serves several purposes: it ensures that all personnel are aware of the status of the generator, and it enables the team to implement any necessary safety measures or additional protocols in dealing with the tagged-out generator.

This communication helps coordinate maintenance and prevents accidental operation of the generator while it is out of service. It also establishes a clear chain of command and accountability in managing the equipment and personnel safety procedures.

The action of rotating all loads to another generator, while important, assumes that the operator is aware of the status of potential overloads or system capacity, which reaffirms the necessity of keeping the engineering officer in the loop.

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy